The Method Of Correctly Cleaning The Compound Flow Closed Cooling Tower
The specific methods of correctly cleaning the compound flow closed cooling tower packing?
The correct cleaning method of the compound flow closed cooling tower packing is as follows:
- Manually clean the slag that falls off in the tower;
2 . Rinse the packing with high pressure water gun repeatedly to remove the washed sludge and scale;
- Dissolve the descaling agent with hot water at about 50°C, and then use the flushing pump to repeatedly flush the packing until the scale is washed out (if the packing has a long service life) , causing aging and collapse, it is recommended to replace the filler), and add bactericidal algaecide to kill biological algae and bacteria;
4.After confirming that all parts of the system are cleaned, drain the sewage;
- Rinse the filler and compound flow closure with water 6. Recover all parts of the system, and the water supply can be used; 7. After all recovery, please ask the management personnel of Party A to check and accept the composite flow closed cooling tower; 8. Evacuate Party B's items and clean the site.